Structural steel firm AMSE Ltd. erected an average of 1,000 tonnes of steel per month at the €80m Abbeylands shopping complex in Ferrybank, County Waterford, it has been revealed.
This project is transforming a seven-acre site into a major shopping attraction in the region with subsequent plans having been announced to develop Ferrybank into a new Irish city
Engineering Director at AMSE, Denis McNelis, explained the fast-track nature of the scheme.
"We were appointed to the project in early 2007 and contracted to detail, fabricate and erect the primary structural steelwork. The structure is a 5 storey beam and column frame, with wide-slab pre-cast concrete floors, and a complex curved Kalzip roof. AMSE were also contracted to provide 1hour fire protection using intumescent paint, with a sealer coat on the basement car park and around the floor perimeters."
"A procurement model was quickly produced by AMSE technicians to allow 5,500 tonnes of steel to be ordered from Corus Mills rollings before the March deadline. This was achieved as AMSE engineers worked in close co-operation with Michael Punch and Partners during this critical stage of the project, to assist in bottoming out the final design."
"This partnership approach allowed 3D procurement models to be drawn in time to meet the extremely tight material procurement window. At the same time, AMSE's operations team liaised with main contractors John Paul Construction throughout February and March to agree sequencing schedules," he added.
"In terms of tonnage this project represents the largest that AMSE has undertaken to date. We utilized 5 of our 10 site crews on this project to meet the accelerated programme. We began erecting on the 9th May and met our completion date in November," Denis explained.
Fabrication commenced at AMSE's production facility in Moate in early April and the first load was delivered to site on the first week in May. In order to satisfy an ambitious accelerated programme, within a confined site due to the phasing of other trades, the structure needed to be planned, fabricated, delivered to site and erected in a carefully planned and choreographed sequence. Foundations, concrete stairwells, lift shafts and 2 storey deep perimeter retaining walls were being constructed concurrently with the steel erection, which determined which areas of the site were available for erection.
This required that the erection of the beam and column structure was divided into 15 phases, and the erection of the roof structure into 4 phases. AMSE erection crews, under the supervision of AMSE contracts manager Rory Harris, erected four levels of steel at a time, using mobile cranes and MEWPs. The roof had to be erected using three site tower cranes as access for mobile cranes was no longer possible.
"Once 4 storeys of steel had been erected for one phase, the pre-cast slabs were lifted into place by tower crane (one of 5 JPC tower cranes on site), as the erection of steel for the next phase began," explained Rory. "By the time phase 10 steel was being erected in late August, the roof of phase 1 was already underway. Close co-ordination between AMSE and JPC on a daily basis, ensured efficient sequencing of erection throughout the project, and optimum programme delivery."
The works increased to include a further 600 tonnes of link-bridge steelwork, which only received planning permission mid-August. With no extension to the original deadline available, AMSE and Corus needed to adapt to meet the additional requirements. AMSE Purchasing Manager Anne Corcoran co-ordinated the procurement of steel from Corus Service Centres Ireland and ensured that all hot-rolled sections were delivered to AMSE's production facility on time, Efficiency and flexibilty allowed AMSE to accommodate the increased scope of works and still meet the original fabrication and erection deadlines.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
20/11/2024
MDE has been awarded the electrical services contract for the Clondalkin School Development Project in Dublin. Working alongside Cunningham Contracts Ltd., the company will serve as the specialist electrical contractor for the construction of new facilities for Gaelscoil na Camóige, Gaelscoil ...
20/11/2024
In celebration of European Week for Waste Reduction, the Northern Ireland Resources Network (NIRN) has launched an environmental education programme to promote zero-waste principles among young people. Three schools from the ABC Borough—St Francis Primary School in Lurgan, St Patrick's Primary ...
20/11/2024
Work has begun at hospital sites across Northern Ireland as part of preparations to eliminate car parking charges by May 2026. Health and Social Care Trusts are installing the necessary infrastructure for a new traffic management system, following the passing of the Hospital Parking Charges Act by ...
20/11/2024
Fine Gael has accused Sinn Féin of abandoning its commitment to protect consumers from rising energy costs, claiming that the party's policies could lead to increased costs for 2.1 million customers. The criticism comes after Sinn Féin's alternative budget last month proposed retaining the ...
20/11/2024
SDLP Agriculture, Environment, and Rural Affairs Spokesperson Patsy McGlone has urged Minister Andrew Muir to take decisive action to protect the environment, rather than launching additional reviews. The comments came after Minister Muir announced a review into environmental governance during an ...
20/11/2024
Alliance Strangford MLAs Kellie Armstrong and Nick Mathison, along with Alliance East Antrim MLA Danny Donnelly, recently visited the tidal research experiment at Queen's University Marine Laboratory (QML) in Strangford. The project, funded by the Centre for Advanced Sustainable Energy (CASE), is ...
19/11/2024
Phoenix Energy has been awarded an international standards accreditation from the British Standards Institution (BSI) in recognition of its inclusive service approach for customers in vulnerable situations. The certification highlights Phoenix Energy's commitment to providing fair, flexible, and ...
19/11/2024
Seating Matters is investing £3.7 million to enhance and improve its manufacturing facilities in Limavady and L'Derry. The company is aiming to support its bold strategy to triple revenue by 2027. Making the announcement while visiting the company's Limavady site Economy Minister Conor Murphy ...
19/11/2024
SDLP Infrastructure Spokesperson Mark H Durkan has urged the Minister and the Executive to take immediate action to address problems within Northern Ireland Water. Mr Durkan warned that the current state of the wastewater system is creating significant delays for infrastructure projects across ...
19/11/2024
Galway City Council will hold a public information evening on affordable housing on Monday, November 25, 2024, from 4pm to 8pm at the Connacht Hotel, Old Dublin Road, Galway. The event will provide an opportunity for the public to learn about how affordable housing operates. Council staff will be ...