Construction Ireland Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
18/09/2024

Unique Solution For Limerick Hospital Excavation

Construction News Image
Groundforce equipment has played a crucial role in the construction of a new extension to University Hospital, Limerick, in Ireland.

The new 9,800m2 acute ward, is built over the existing emergency department and dialysis unit and consists of 96 ensuite single rooms over four floors.

As part of the project, main contractor Sisk was required to build a new lift core, adjoining the existing hospital building and lower-level car park, to service the new structure.

The lift core rises from an 8m-deep excavation dug immediately adjacent to the existing building. The bottom 4m of this excavation was in the bedrock, comprising a hard granite material, and was self-supporting. The upper 4m was in the overlying soil and required temporary support to prevent any collapse.

This was the element of the project that required the services of Groundforce.

"The excavation needed temporary support on three sides - the fourth side was the wall of the existing hospital building," explained Groundforce director Joseph Lenihan.

The usual method employed by Groundforce is to support the sheet-piled retaining walls with modular extendable waling beams around the perimeter and hydraulic props spanning the excavation from side to side and bearing on the waling beams.

However, the size of this excavation (measuring approximately 14m x 17.5m) and its location against the wall of an existing building required a different approach.

"It was acceptable to the client for the adjoining wall to take a shear load from the shoring system but not a point load," said Joseph Lenihan, "Therefore the shoring system had to rely on lateral restraint from the adjacent ground."

-- Advertisement --

The shoring system comprised two levels of Mega Brace frame supporting the 5m-long Larssen L603 sheet piles lining the excavation and four of Groundforce's MP150 modular hydraulic props installed as corner struts at the end of the excavation furthest from the hospital building.

Groundforce also supplied the MS4 piling hammer to install the sheet-piles. Perimeter safety was provided in the form of Groundforce's Edgesafe barrier and davit-arm rescue system.

The lateral loads from the three braced sides of the excavation were transferred along the line of the sheet-piled retaining walls which, together with the earth behind them, provided a shear key to prevent any point load transferring to the adjacent building.

The shoring system design was developed jointly by Groundforce and Sisk's temporary works department and approved by the project's consulting engineer, Arup.

"During the design stage a concern was raised by the Sisk design team regarding the transfer of the load to the shear key," said Joseph Lenihan. "A typical hydraulic bracing system is pressurised to prevent any lateral movement. However, this lack of movement would not allow the shear key to take effect - the adjacent ground would not be given the chance to take the load.

"The solution was to not lock-off the ram element of the frame, thereby allowing it to contract once the system became loaded. This allowed a certain amount of movement and ensured that no point load was transferred to the adjacent wall.

"It's fair to say that we've never done this before," he added.

The unique requirements of this operation demanded close collaboration between designers from Groundforce and Sisk's temporary works department.

"There was a lot of design development required, not just for the shoring system itself but for the sequence of its installation and removal," said Sisk's project manager Stephen Geraghty.

"In fact, almost as much design went into the removal of the temporary works as for the installation. The sequence of backfilling to a certain level, concreting and removing the bracing had to be carefully planned."

Carrying out the work so close to the existing building brought the added risk of disturbance to the hospital's staff and patients. Noise and vibration therefore had to be kept to the absolute minimum and was carefully monitored.

"When it came to excavating through the rock we had to bring in a specialist to drill it out in small sections instead of going in there with heavy machinery. The excavation was quite slow: the first two or three weeks were spent just drilling/hydraulic breaking rock," said Stephen Geraghty.

During the works, weekly design workshops ensured that the temporary works element remained under scrutiny.

"It was certainly tricky. But we kept in constant dialogue with Groundforce and I can't complement them enough," he added.

Latest Construction News

20/11/2024

MDE has been awarded the electrical services contract for the Clondalkin School Development Project in Dublin. Working alongside Cunningham Contracts Ltd., the company will serve as the specialist electrical contractor for the construction of new facilities for Gaelscoil na Camóige, Gaelscoil ...
20/11/2024

In celebration of European Week for Waste Reduction, the Northern Ireland Resources Network (NIRN) has launched an environmental education programme to promote zero-waste principles among young people. Three schools from the ABC Borough—St Francis Primary School in Lurgan, St Patrick's Primary ...
20/11/2024

Work has begun at hospital sites across Northern Ireland as part of preparations to eliminate car parking charges by May 2026. Health and Social Care Trusts are installing the necessary infrastructure for a new traffic management system, following the passing of the Hospital Parking Charges Act by ...
20/11/2024

Fine Gael has accused Sinn Féin of abandoning its commitment to protect consumers from rising energy costs, claiming that the party's policies could lead to increased costs for 2.1 million customers. The criticism comes after Sinn Féin's alternative budget last month proposed retaining the ...
20/11/2024

SDLP Agriculture, Environment, and Rural Affairs Spokesperson Patsy McGlone has urged Minister Andrew Muir to take decisive action to protect the environment, rather than launching additional reviews. The comments came after Minister Muir announced a review into environmental governance during an ...
20/11/2024

Alliance Strangford MLAs Kellie Armstrong and Nick Mathison, along with Alliance East Antrim MLA Danny Donnelly, recently visited the tidal research experiment at Queen's University Marine Laboratory (QML) in Strangford. The project, funded by the Centre for Advanced Sustainable Energy (CASE), is ...
19/11/2024

Phoenix Energy has been awarded an international standards accreditation from the British Standards Institution (BSI) in recognition of its inclusive service approach for customers in vulnerable situations. The certification highlights Phoenix Energy's commitment to providing fair, flexible, and ...
19/11/2024

Seating Matters is investing £3.7 million to enhance and improve its manufacturing facilities in Limavady and L'Derry. The company is aiming to support its bold strategy to triple revenue by 2027. Making the announcement while visiting the company's Limavady site Economy Minister Conor Murphy ...
19/11/2024

SDLP Infrastructure Spokesperson Mark H Durkan has urged the Minister and the Executive to take immediate action to address problems within Northern Ireland Water. Mr Durkan warned that the current state of the wastewater system is creating significant delays for infrastructure projects across ...
19/11/2024

Galway City Council will hold a public information evening on affordable housing on Monday, November 25, 2024, from 4pm to 8pm at the Connacht Hotel, Old Dublin Road, Galway. The event will provide an opportunity for the public to learn about how affordable housing operates. Council staff will be ...
Brady Insurance Services LtdTipperary Crane HireActive Electrical LTDBuilders FortSolar Energy PLCClean Solar Solutions IrelandTapco Roofing ProductsDerrypark Construction LtdGreen City Paving & LandscapingSkill Ireland Training
Terms and Conditions
2024/11/21 13:10:21