Kesh Footbridge has been reopened after FP McCann successfully completed construction of a new retaining wall and associated in-river works in Kesh.
At nearly 8m tall, FP McCann and subcontractor, Milligan Bros, were presented with a very challenging task of constructing the wall adjacent to the often unpredictable Kesh River coupled with a very constricted site that was also adjacent to private property with the only access to the site via the congested A35 at the bridge.
Initial works involved demolition of the existing stone clad reinforced concrete wall as well as demolition of old masonry river wall and existing sheds. The challenging ground conditions were made even more difficult with the existing varying rock bed forcing a change to the design of the temporary works design.
VP Groundforce designed a triple braced sheet pile cofferdam with a top-down construction sequence deployed to allow a formation depth approximately 2m below the existing river bed level of the Kesh River.
With inclement weather during the summer of 2023, the site was met with numerous flood events adding to the precarious conditions being faced on site. To mitigate against further weather depending masonry works, the river face of the wall was constructed using a stone clad pattern liner within the formwork.
All concrete for the works was supplied from our Lisnaskea depot who helped with the solution of using steel fibre reinforced underwater concrete when faced with incoming water ingress during infill concreting operations where dewatering operations were not viable.
FP McCann's Ennis stone was used to complement the internal face of the retaining walls as well as tying into the existing masonry walls. FP McCann's primary rock armour was also used within the river as scour protection to the existing masonry walls. Surfacing works were also completed in the carpark.
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
22/11/2024
A contract to design the Sandymount Flood Defence Scheme in Dublin has been awarded to Jacobs by the City Council. Sandymount is one of the city areas most vulnerable to coastal flooding and is also, separately, at risk from surface water flooding, i.e. run-off from rainfall. The contract ...
22/11/2024
Northern Ireland construction company Farrans has scooped a Highly Commended All-Ireland Occupational Safety Award. The company's SHE team members Joe Loughan and Ryan Carson attended the recent premier event, which were held in the Great Southern Hotel, Killarney, to be presented with a ...
22/11/2024
A 'Back to the 80s' themed charity ball, which was sponsored by a number of construction companies, has helped raise a record-breaking £118,000 profit for WaterAid. The international charity's event was held recently in Titanic Belfast will all of the funds raised going towards the WaterAid ...
22/11/2024
The M3 Lagan Bridge in Belfast will undergo urgent repair work from Tuesday, November 26, in order to replace damaged joints. As a result of the essential requirement to carry out these works, and to ensure the availability of specialist contractors, a series of lane closures will be in place ...
22/11/2024
Scheduled resurfacing works at the Syndenham bypass in Belfast, which were due to continue this weekend, will now not go ahead and the road will remain open. This comes as a result of a yellow Met office warning put in place for part of Saturday. An overnight closure will remain in place between ...
22/11/2024
Works to improve Kinsale's water supply in County Cork are set to commence next week. The project entails the replacement of over 500 metres of old watermains that are prone to frequent bursts and leakage with new modern pipes. The works will be carried out by Ward and Burke Construction Ltd on ...
22/11/2024
The first phase of sewer relining works on the Shore Road in Belfast has been successfully completed ahead of schedule by contractor Murphy Dawson WAM, NI Water has announced. As a result, the road has now fully reopened earlier than anticipated. The work to date has seen over half a kilometre of ...
22/11/2024
Leakage reduction works and water supply improvements to homes and businesses in Dublin 2 have been completed. The works, which were carried out on behalf of Uisce Éireann by GMC Utilities Group Ltd, involved the replacement of 180 metres of ageing water pipes between the junction of D'Olier ...
22/11/2024
CRH member company Roadstone has completed a major plant and equipment investment at its quarry, aggregates, and concrete products sites in the Republic of Ireland. The equipment – supplied to them by Komatsu and Metso distributors in Ireland, McHale Plant Sales – included Komatsu WA475 and WA600 ...
22/11/2024
A new member has been added to the Ministerial Advisory Group (MAG) for Architecture and the Built Environment for Northern Ireland. Mrs Suzanne McCoy has been announced as the latest MAG addition by Communities Minister, Gordon Lyons MLA, and will begin her role from December 1, 2024 until ...