FP McCann has made significant progress on the 3G Pitch & Associated Works at Lough Moss Leisure Centre in Carryduff for Lisburn & Castlereagh City Council (L&CCC).
By January 2024, several significant works were completed. The project began in early August 2023 with the replacement of the culvert section running under the pitch, which was subsequently completed and documented with CCTV footage sent to the statutory body for a 14-week review and approval period. The culvert headwall required a revised design. The existing carpeted pitch was removed and recycled, and the tar base was excavated using a planer, with the planings left in situ for testing and potential reuse as they comply with the appropriate specifications. Additionally, the old floodlighting was disconnected and the columns were removed. By January 2024, the topsoil had been stripped from the grass pitch.
By May 2024, significant progress was made on the main pitch works area, the cut and works were completed, followed by the installation of drainage, including precast manholes and new lateral drainage lines under the pitch. An attenuation tank for the drainage system was excavated, a gravel layer was laid and the tank was installed by a specialist subcontractor. Foundations for the new floodlights have been excavated and the ducting installed. Precast concrete piles were installed and a mud mat was poured for the retaining wall and floodlight foundations. The culvert headwall, grill, steps and outer fencing have all been installed, with only the handrail remaining to complete the work on this side of the path. Additionally, the new coach bay in the car park is complete to the base layer and work commenced on the 17 additional parking spaces on the Leisure Centre side of the dog park.
As of June 2024, a progress report has revealed that the new overflow car park works are now complete. The main car park works, which included adding a new coach bay, realigning spaces and resurfacing the area, are also finished. In the main pitch area, all drainage has been installed, the retaining wall has been built and the adjacent path will be reopened to the public in the coming days. Installation of fence posts for the new pitch fencing and ball stop fencing is ongoing.
The project is scheduled for completion in November 2024.
Construction News
24/07/2024
Significant Progress Made On Carryduff Leisure Centre Project


11/03/2025
Major redevelopment works have commenced at Northern Ireland premier luxury hospitality group Galgorm Collection's Roe Valley Resort in County L'Derry, marking the first of four £5m investment programmes.
The rebranded Roe Valley Resort, formerly Roe Park Resort, will see its investment split this

11/03/2025
The latest Assured Skills Collaborative Welding Academy at South West College (SWC) in Cookstown, County Tyrone, will commence next month.
Fully funded by the Department for the Economy, this Academy is offering an opportunity for 12 individuals to receive industry standard welding training that wi

11/03/2025
Plans for a new residential housing development on 1.7 acres of Belfast city centre land are moving positively forward.
Clanmil Housing Association has been appointed to develop the mixed-use scheme on the land which is owned by Belfast City Council and the Department for Communities.
The project

11/03/2025
A call for applications has been launched for the fourth year of the All-Ireland Heritage Skills Programme.
The programme, developed by The King's Foundation in partnership with Northern Ireland's Department for Communities and the Heritage Council, will support seven aspiring craftspeople with an

11/03/2025
An allocation of £18m from the Transformation Programme for two Northern Ireland infrastructure projects have been welcomed by Minister Liz Kimmons.
The funding will be divided between two projects, which include the Urban Drainage pilot project that will help transform the way in which rainwater i

11/03/2025
A large vacant property based in Waterford city centre will be converted into a centre for homeless women following government approval.
The Minister for Housing, Local Government and Heritage, James Browne, green-lit plans to use the Repair and Leasing Scheme (RLS) to renovate the St John's Presby

11/03/2025
Representatives from the Construction Industry Federation (CIF) recently met with Senior Planning and Infrastructure council staff from Galway City to strengthen the partnership between the public and private sectors in delivering much-needed housing units within the area.
The meeting provided an o

11/03/2025
Northern Ireland construction company McLaughlin & Harvey, working in collaboration with the UK Atomic Energy Authority (UKAEA), has completed the first phase of its redevelopment project at Culham Science Centre.
This redevelopment is crucial for supporting the UK’s goal of delivering sustainable

11/03/2025
A major infrastructural project in Letterkenny, County Donegal, will begin in the coming weeks as site investigation works are set to commence.
Whiteford Geoservices Ltd will carry out the works on behalf of utilities company Uisce Éireann.
The Letterkenny Water Supply Zone project works will invo

11/03/2025
Normal operations have resumed at the Gorey Water Treatment Plant in County Wexford after successful works were carried out by utilities company Uisce Éireann.
An interruption to the water supply impacted customers in Ballyminaun, Gorey and surrounding areas, however, Uisce Éireann announced this i