Ballykelly Wastewater Plant has been significantly upgraded with a new solar panel system.
NI Water's first battery energy storage system was installed at the new Ballykelly Wastewater Treatment Works (WwTW).
Last year, NI Water announced the completion of the overall £5 million investment to upgrade Ballykelly WwTW, providing a new wastewater treatment approach, utilising reed beds as part of the treatment process, providing a natural, long-term and resilient solution. The Ballykelly plant is leading the way with this sustainable solution to wastewater treatment, which maximises the use of renewables as part of an integrated solution. This new battery energy storage system will further enhance the efficiency of the plant through increased use of solar energy.
Mark Brownlee NI Water Senior Capital Project Manager said: "The aim of the new battery system is to enable the plant to operate using 100% locally generated solar power for as much of the year as possible. In winter months, during periods of lower solar generation, the battery system can be topped up from the grid using off-peak cheaper energy tariffs.
"This innovative system, which was developed in-house, is the first of its kind for NI Water and will bring many efficiency benefits and cost savings to the company in light of rising energy prices."
The battery system will be used in an innovative way to drive costs down during high demand periods in the winter by maximising the use of both the electricity network and the Solar Panel System. Energy can be stored and released flexibly to reduce costs during peak periods and decrease the demand on the grid.
Time and date
CONSTRUCTION DIRECTORY
Construction News
29/11/2022
Landmark Installation At Ballykelly Wastewater Plant Complete
Latest Construction News
22/11/2024
A contract to design the Sandymount Flood Defence Scheme in Dublin has been awarded to Jacobs by the City Council. Sandymount is one of the city areas most vulnerable to coastal flooding and is also, separately, at risk from surface water flooding, i.e. run-off from rainfall. The contract ...
22/11/2024
Northern Ireland construction company Farrans has scooped a Highly Commended All-Ireland Occupational Safety Award. The company's SHE team members Joe Loughan and Ryan Carson attended the recent premier event, which were held in the Great Southern Hotel, Killarney, to be presented with a ...
22/11/2024
A 'Back to the 80s' themed charity ball, which was sponsored by a number of construction companies, has helped raise a record-breaking £118,000 profit for WaterAid. The international charity's event was held recently in Titanic Belfast will all of the funds raised going towards the WaterAid ...
22/11/2024
The M3 Lagan Bridge in Belfast will undergo urgent repair work from Tuesday, November 26, in order to replace damaged joints. As a result of the essential requirement to carry out these works, and to ensure the availability of specialist contractors, a series of lane closures will be in place ...
22/11/2024
Scheduled resurfacing works at the Syndenham bypass in Belfast, which were due to continue this weekend, will now not go ahead and the road will remain open. This comes as a result of a yellow Met office warning put in place for part of Saturday. An overnight closure will remain in place between ...
22/11/2024
Works to improve Kinsale's water supply in County Cork are set to commence next week. The project entails the replacement of over 500 metres of old watermains that are prone to frequent bursts and leakage with new modern pipes. The works will be carried out by Ward and Burke Construction Ltd on ...
22/11/2024
The first phase of sewer relining works on the Shore Road in Belfast has been successfully completed ahead of schedule by contractor Murphy Dawson WAM, NI Water has announced. As a result, the road has now fully reopened earlier than anticipated. The work to date has seen over half a kilometre of ...
22/11/2024
Leakage reduction works and water supply improvements to homes and businesses in Dublin 2 have been completed. The works, which were carried out on behalf of Uisce Éireann by GMC Utilities Group Ltd, involved the replacement of 180 metres of ageing water pipes between the junction of D'Olier ...
22/11/2024
CRH member company Roadstone has completed a major plant and equipment investment at its quarry, aggregates, and concrete products sites in the Republic of Ireland. The equipment – supplied to them by Komatsu and Metso distributors in Ireland, McHale Plant Sales – included Komatsu WA475 and WA600 ...
22/11/2024
A new member has been added to the Ministerial Advisory Group (MAG) for Architecture and the Built Environment for Northern Ireland. Mrs Suzanne McCoy has been announced as the latest MAG addition by Communities Minister, Gordon Lyons MLA, and will begin her role from December 1, 2024 until ...