Construction firm GRAHAM has completed part of a railway bridge replacement and refurbishment works programme, incorporating a 72-hour single event possession, on the Ballymena to Coleraine rail line.
Three major sites, namely the Braid Bridge, Coolderry Bridge and the Culbreen Bridge, were all part of the Translink commissioned contract that was awarded in late January 2021.
Before construction work could commence, an intensive two month planning process was required, which resulted in the identification of a more efficient 72-hour single possession solution as opposed to an original two-pronged possession plan totalling 108 hours.
This innovative approach considerably reduced disruption to the rail network by a full day and a half (36 hours) and also allowed the GRAHAM team to de-risk the programme for two of the bridges.
As part of the package of works, the existing Culbreen Bridge structure was demolished, meaning costly ongoing maintenance is no longer required.
The underside of the entire deck and outer edges of the Coolderry Bridge underwent hydro-demolition before the existing steelwork was drilled for reinforcement to be laid and the surface shot-creted. These important bridge strengthening works, conducted for the first time during a disruptive rail possession, have restored the bridge’s weight restriction to its original design of 40 tonnes.
The Braid Bridge works, on a four-arch masonry structure over the River Braid in Ballymena, involved the removal of 70m of twin track, sleepers, ballast and structural fill. Subsequently, the bridge was waterproofed and reinstated, extending the life span of the structure. The track was also re-laid, welded and stressed.
The works were completed ahead of programme, allowing early handback of the network.
Andrew Henry, GRAHAM Contracts Manager, said: "Generally, a multi-site scheme of this complexity would require a prolonged period of advanced planning and programming, sometimes as much as nine months. Demonstrating our technical competency, we were able to develop a more effective solution of a 72-hour single event possession in as little as two months. This ensured a more efficient process and reduced disruption to the network. Significantly, our waterproofing work, involving loose laid sheeting, was the first of its type to be carried out on a 'live' Translink asset for a considerable length of time.
"Overall, our planning and delivery reflect the successful long-term collaborative relationship that we have developed with Translink, and we look forward to working in partnership on further schemes to future-proof the local rail network."
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
20/11/2024
MDE has been awarded the electrical services contract for the Clondalkin School Development Project in Dublin. Working alongside Cunningham Contracts Ltd., the company will serve as the specialist electrical contractor for the construction of new facilities for Gaelscoil na Camóige, Gaelscoil ...
20/11/2024
In celebration of European Week for Waste Reduction, the Northern Ireland Resources Network (NIRN) has launched an environmental education programme to promote zero-waste principles among young people. Three schools from the ABC Borough—St Francis Primary School in Lurgan, St Patrick's Primary ...
20/11/2024
Work has begun at hospital sites across Northern Ireland as part of preparations to eliminate car parking charges by May 2026. Health and Social Care Trusts are installing the necessary infrastructure for a new traffic management system, following the passing of the Hospital Parking Charges Act by ...
20/11/2024
Fine Gael has accused Sinn Féin of abandoning its commitment to protect consumers from rising energy costs, claiming that the party's policies could lead to increased costs for 2.1 million customers. The criticism comes after Sinn Féin's alternative budget last month proposed retaining the ...
20/11/2024
SDLP Agriculture, Environment, and Rural Affairs Spokesperson Patsy McGlone has urged Minister Andrew Muir to take decisive action to protect the environment, rather than launching additional reviews. The comments came after Minister Muir announced a review into environmental governance during an ...
20/11/2024
Alliance Strangford MLAs Kellie Armstrong and Nick Mathison, along with Alliance East Antrim MLA Danny Donnelly, recently visited the tidal research experiment at Queen's University Marine Laboratory (QML) in Strangford. The project, funded by the Centre for Advanced Sustainable Energy (CASE), is ...
19/11/2024
Phoenix Energy has been awarded an international standards accreditation from the British Standards Institution (BSI) in recognition of its inclusive service approach for customers in vulnerable situations. The certification highlights Phoenix Energy's commitment to providing fair, flexible, and ...
19/11/2024
Seating Matters is investing £3.7 million to enhance and improve its manufacturing facilities in Limavady and L'Derry. The company is aiming to support its bold strategy to triple revenue by 2027. Making the announcement while visiting the company's Limavady site Economy Minister Conor Murphy ...
19/11/2024
SDLP Infrastructure Spokesperson Mark H Durkan has urged the Minister and the Executive to take immediate action to address problems within Northern Ireland Water. Mr Durkan warned that the current state of the wastewater system is creating significant delays for infrastructure projects across ...
19/11/2024
Galway City Council will hold a public information evening on affordable housing on Monday, November 25, 2024, from 4pm to 8pm at the Connacht Hotel, Old Dublin Road, Galway. The event will provide an opportunity for the public to learn about how affordable housing operates. Council staff will be ...