Construction Ireland Construction Directory
Time and date
CONSTRUCTION DIRECTORY
Share this page
Construction News
05/11/2018

FP McCann Helps Support Capital Scheme In New Zealand

Construction News Image
NI manufacturer and supplier of precast concrete solutions, FP McCann has successfully supported a Wellington Water capital scheme in New Zealand.

The company's back-bolted caisson shaft segment rings were utilised to build a 6.5m diameter deep waste water pumping station in the heart of Wellington's Central Business District (CBD)

The new sewer infrastructure project will also relieve pressure on the existing pumping stations, thereby reducing the possibility of overflow into the harbour.

The 6.50m internal diameter shaft was sunk from ground level using the caisson method. Sinking was partially aided by four hydraulic jacks with FP McCann's back-bolted standard precast concrete rings forming each complete section of the shaft wall. The concrete cutting shoe was initially installed and subsequent rings placed on top, thereby allowing the shaft to sink under its own weight, helped with the jacks and some partial undermining of the hard gravel layer beneath the cutter shoe. Once the shaft build was complete, mass concrete was poured into the base to form a 1.5m deep plug, on top of which the structural floor is currently being constructed. Back grouting of the shaft walls will complete the solid, water tight chamber.

-- Advertisement --

The contract to build the shaft and other associated pipeline upgrade engineering works was awarded to Brian Perry Civil (PBC), part of the NZX/ASX listed Fletcher Building group.

Commenting on the shaft build, Daniel Doyle, Project Engineer of BPC said: "The precast segmental caisson provided the most efficient solution to deal with the limited working space available and to handle the water table that sat at 4.5 metres below ground level. The much smaller footprint over other options considered, reduced the volume of material to be removed and also allowed us to retain existing street light poles and a protected tree, that otherwise would have had to be removed. From a safety aspect, workers didn't need to enter the shaft until the base plug had been poured."

In leading discussions with Wellington Water and FP McCann, Andrew Burgess, BPC Wellington Regional Manager said: "The key was to ensure that the caisson could withstand the seismic loads that the structure could be subject to. Wellington has some of the highest earthquake loads in the country, so ensuring that the pump station could withstand the design seismic loads was critical. Wellington Water and consultant GHD were keen to progress our solution and we offered to undertake further design modelling to demonstrate compliance. FP McCann were incredibly helpful in providing the design information that they had, which we could then model to suit NZ conditions and building code requirements."

Stuart Carson, National Tunnels & Shafts Manager for FP McCann added: "The construction methodology adopting the precast segmental caisson shaft sinking process is the first of its kind in New Zealand and we're very proud to have played a big part in this project. Moving forward, we see a strong partnership developing between ourselves, BPC and their client base."

(CM/MH)

Latest Construction News

22/11/2024

A contract to design the Sandymount Flood Defence Scheme in Dublin has been awarded to Jacobs by the City Council. Sandymount is one of the city areas most vulnerable to coastal flooding and is also, separately, at risk from surface water flooding, i.e. run-off from rainfall. The contract ...
22/11/2024

Northern Ireland construction company Farrans has scooped a Highly Commended All-Ireland Occupational Safety Award. The company's SHE team members Joe Loughan and Ryan Carson attended the recent premier event, which were held in the Great Southern Hotel, Killarney, to be presented with a ...
22/11/2024

A 'Back to the 80s' themed charity ball, which was sponsored by a number of construction companies, has helped raise a record-breaking £118,000 profit for WaterAid. The international charity's event was held recently in Titanic Belfast will all of the funds raised going towards the WaterAid ...
22/11/2024

The M3 Lagan Bridge in Belfast will undergo urgent repair work from Tuesday, November 26, in order to replace damaged joints. As a result of the essential requirement to carry out these works, and to ensure the availability of specialist contractors, a series of lane closures will be in place ...
22/11/2024

Scheduled resurfacing works at the Syndenham bypass in Belfast, which were due to continue this weekend, will now not go ahead and the road will remain open. This comes as a result of a yellow Met office warning put in place for part of Saturday. An overnight closure will remain in place between ...
22/11/2024

Works to improve Kinsale's water supply in County Cork are set to commence next week. The project entails the replacement of over 500 metres of old watermains that are prone to frequent bursts and leakage with new modern pipes. The works will be carried out by Ward and Burke Construction Ltd on ...
22/11/2024

The first phase of sewer relining works on the Shore Road in Belfast has been successfully completed ahead of schedule by contractor Murphy Dawson WAM, NI Water has announced. As a result, the road has now fully reopened earlier than anticipated. The work to date has seen over half a kilometre of ...
22/11/2024

Leakage reduction works and water supply improvements to homes and businesses in Dublin 2 have been completed. The works, which were carried out on behalf of Uisce Éireann by GMC Utilities Group Ltd, involved the replacement of 180 metres of ageing water pipes between the junction of D'Olier ...
22/11/2024

CRH member company Roadstone has completed a major plant and equipment investment at its quarry, aggregates, and concrete products sites in the Republic of Ireland. The equipment – supplied to them by Komatsu and Metso distributors in Ireland, McHale Plant Sales – included Komatsu WA475 and WA600 ...
22/11/2024

A new member has been added to the Ministerial Advisory Group (MAG) for Architecture and the Built Environment for Northern Ireland. Mrs Suzanne McCoy has been announced as the latest MAG addition by Communities Minister, Gordon Lyons MLA, and will begin her role from December 1, 2024 until ...
Kwik Floor ScreedRTS Heating & CoolingMaccaferri LtdAtlas Winch & Hoist Services (Southern) LimitedAPA Facade Systems (UK) LtdBDRs LimitedHi-Tec ConstructionPEFC [Ireland] LtdPro Roofers GalwayBrady Insurance Services Ltd
Terms and Conditions
2024/11/23 09:38:57