The contentious A5 upgrade is to face a public inquiry next month.
Plans to dual the 85km route, spanning Aughnacloy to Newbuildings, have attracted over 2,400 objections.
Protesters have argued that the carriageway will cause loss of land and disruption to communities. They say the road, which will only have eight access points and may not carry enough traffic to warrant the £850m outlay.
The Republic of Ireland is contributing £400m to the the A5 and A8 upgrade.
Meanwhile construction of the A26 between Glarryford and Drones Road has been shelved for at least four years due to lack of funds.
Ballymena councillors were informed via a letter from the Regional Development Minister Conor Murphy's acting Private Secretary that the scheme's delivery will be dependent on the allocation of finances in the next Budget period.
The letter said that "unfortunately, when these competing priorities are taken into consideration, the funding allocated in Budget 2010 will not enable construction of the A26 between Glarryford and the A44 Drones Road to start in the next four year period".
See: A5 Road Scheme Protest Redundant?
(GK/KMcA)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
03/12/2024
A £12 million investment will be made by one of the UK & Ireland's leading construction manufacturers, Tobermore, to expand its operations. Kick-starting the expansion, the L'Derry-based company will invest £4 million in new jobs, including the creation of a dedicated technical design team to ...
03/12/2024
Dankse Bank have supported an investment totalling over £3.1million to expand the Ballymena headquarters of Northern Ireland's leading precast concrete manufacturer and supplier, Moore Concrete Products Ltd. The expansion will include building three new factories totalling 4,750square metres for ...
03/12/2024
The second phase of construction works at Kiltipper Park in South Dublin were officially marked recently by a sod-turning event. The works about to commence will include the construction of an extended car park; footpath and northern pedestrian entrance improvements; sports pitch construction and ...
03/12/2024
Ballyclare-based housebuilder Hagan Homes has appointed a new Managing Director. Jim Burke, who boasts over 35 years of dedicated service within the Northern Ireland company resulting in a wealth of experience and knowledge of the industry, will take up the role as Hagan Homes embarks on a ...
03/12/2024
Northern Ireland construction firm GRAHAM has received National GOLD honours for the Belfast-based Nelson Place Student Accommodation in the Climate Change Benefits category at this year's Green Apple Awards. The state-of-the-art facility boasts the first two blue roofs to be installed in Northern ...
03/12/2024
Works to replace over 8.7km of ageing water mains with new, modern pipes in Sligo have successfully been completed, Uisce Éireann has announced. As a result, customers to the south of Sligo town are benefitting from a more secure and reliable water supply. The recent works included three sections ...
03/12/2024
A transformative project at the Melvin Recreational and Resource Complex in Garrison, County Fermanagh, has successfully been completed. The project, which was delivered under the Covid Recovery Small Settlement Regeneration Programme, saw the Complex's bedrooms and dormitory rooms enhanced into ...
03/12/2024
A public consultation is now open regarding the newly launched Draft Dromore Place Plan by Armagh City, Banbridge and Craigavon Borough Council. The plan outlines key projects to rejuvenate the area and enhance its social, economic and environmental well-being, with input included from 614 local ...
03/12/2024
Road construction and utility works are currently ongoing in Ballina, Co. Tipperary. The works, which began yesterday, resulted in the urgent closure of the R-496-13 road from the junction at Roolagh at R-494-0 for a 100m section. This closure will remain in place until 11.59pm on Saturday, ...
03/12/2024
Ground investigation works are set to commence from next week in Wicklow. The works, which will take place on the N81 at Hollywood Junction (approximately 0.25km either side of the junction), will begin from Monday, December 9, until Thursday, December 12. Temporary traffic management will be in ...