An infrastructure contract in Co Donegal is being delayed after it emerged that the renewal works to Main Street in the town of Milford has suffered a fresh setback.
After an eight-year wait and a street protest, work commenced at the beginning of March on the €1.3 million renewal works in the town.
However, a contractual disagreement between the main contractor and Donegal County Council has delayed progress on the works by at least a month.
The matter was discussed at length between local councillors and council officials at a secret meeting, held behind closed doors.
It later emerged that the contractor "lost a lot of time" during the dispute with the council but had since made assurances that "he will make up for lost time".
According to the council it was originally anticipated works should be completed within a 26-week period from the beginning of March.
A council spokesperson said that the contractor has provided the council with a schedule of works, and, as far as the council is concerned, the outstanding issue has been resolved and can now get underway again.
Following the completion of urban renewal works in 1998, a public consultation process was undertaken whereby it was agreed that renewal works along the Main Street should be prioritised.
It was recognised that alternative off-street car parking provision would be required to facilitate the progression of any renewal works on the Main Street.
The council has recently completed the acquisition of suitable lands to accommodate the construction of a new car park and link road prior to the completion of renewal works along the Main street.
In order to ensure the minimum possible local disruption, the project will be completed in two consecutive phases.
The first phase will involve the development of an off-street car park scheme plus the creation of a link road between the Kilmacrennan Road and the Church Road.
The second phase will comprise Urban Renewal works along the Main Street between the Diamond and Public Service Centre road consisting of undergrounding of overhead services, new decorative lighting, street furniture and provision of new footpaths.
(BMcC/GK)
Time and date
CONSTRUCTION DIRECTORY
Latest Construction News
03/12/2024
A £12 million investment will be made by one of the UK & Ireland's leading construction manufacturers, Tobermore, to expand its operations. Kick-starting the expansion, the L'Derry-based company will invest £4 million in new jobs, including the creation of a dedicated technical design team to ...
03/12/2024
Dankse Bank have supported an investment totalling over £3.1million to expand the Ballymena headquarters of Northern Ireland's leading precast concrete manufacturer and supplier, Moore Concrete Products Ltd. The expansion will include building three new factories totalling 4,750square metres for ...
03/12/2024
The second phase of construction works at Kiltipper Park in South Dublin were officially marked recently by a sod-turning event. The works about to commence will include the construction of an extended car park; footpath and northern pedestrian entrance improvements; sports pitch construction and ...
03/12/2024
Ballyclare-based housebuilder Hagan Homes has appointed a new Managing Director. Jim Burke, who boasts over 35 years of dedicated service within the Northern Ireland company resulting in a wealth of experience and knowledge of the industry, will take up the role as Hagan Homes embarks on a ...
03/12/2024
Northern Ireland construction firm GRAHAM has received National GOLD honours for the Belfast-based Nelson Place Student Accommodation in the Climate Change Benefits category at this year's Green Apple Awards. The state-of-the-art facility boasts the first two blue roofs to be installed in Northern ...
03/12/2024
Works to replace over 8.7km of ageing water mains with new, modern pipes in Sligo have successfully been completed, Uisce Éireann has announced. As a result, customers to the south of Sligo town are benefitting from a more secure and reliable water supply. The recent works included three sections ...
03/12/2024
A transformative project at the Melvin Recreational and Resource Complex in Garrison, County Fermanagh, has successfully been completed. The project, which was delivered under the Covid Recovery Small Settlement Regeneration Programme, saw the Complex's bedrooms and dormitory rooms enhanced into ...
03/12/2024
A public consultation is now open regarding the newly launched Draft Dromore Place Plan by Armagh City, Banbridge and Craigavon Borough Council. The plan outlines key projects to rejuvenate the area and enhance its social, economic and environmental well-being, with input included from 614 local ...
03/12/2024
Road construction and utility works are currently ongoing in Ballina, Co. Tipperary. The works, which began yesterday, resulted in the urgent closure of the R-496-13 road from the junction at Roolagh at R-494-0 for a 100m section. This closure will remain in place until 11.59pm on Saturday, ...
03/12/2024
Ground investigation works are set to commence from next week in Wicklow. The works, which will take place on the N81 at Hollywood Junction (approximately 0.25km either side of the junction), will begin from Monday, December 9, until Thursday, December 12. Temporary traffic management will be in ...